About SAHS > High School Facility Facts
| Site Area |
104 acres in Franconia Township |
| Building Size |
445,000 square feet |
Student capacity (grades 9-12)- 2720 by PDE methodology
- Regular and special education classrooms- 78
- Science labs - 22
- Classrooms for other specific curriculums- 23 (art, business, family & consumer sciences, music, technology ed, tv studio/ video editing lab)
- Physical education instructional spaces - 5 (main gym -2300 seats, auxiliary gym- 180 seats, wrestling room, fitness/ weight room, natatorium with 10 lanes, 2 diving boards, 180 seats)
- Core facilities - library, auditorium (842 seats) with full stage, balcony, dressing and storage rooms, cafeteria/ kitchen (625) with food court serving, large group rooms, small group rooms
- Administrative areas - main office, house offices (2), guidance/ student services suite, health suite, department planning centers
|
Site Facilities- parking spaces- 912 plus additional overflow spaces
- dedicated bus loading zone- 45 buses
- multi-purpose stadium- 4000 grandstand seats
- artificial turf field lined for football, soccer and field hockey
- urethane rubber surfaced running track
- natural grass multi-purpose fields- 7
- softball fields- 3 tennis courts- 6
|
| Design Team |
Breslin Ridyard Fadero Architects
Consolidated Engineers- mechanical & electrical design
Barry Isett and Associates- civil & structural design
Counsilman/ Hunsaker Associates- swimming pool design
Glenn Bush and Associates- kitchen/ & food court design
Metropolitan Acoustics- sound & acoustical design
D'huy Engineering- construction management
|
| Prime Contractors |
Skepton Construction (general contractor)
Farfield Electric (electrical contractor)
Boro Mechanical (HVAC contractor)
JBM Plumbing (plumbing contractor)
Guy Cooper Sprinkler (fire suppression contractor)
NRG (data/ communications contractor)
Acapulco Pools (swimming pool contractor)
Todd Devin (food service equipment contractor)
|
| Total Value of Contracts Awarded |
$ 89 million |
| Construction Started |
May 2006 |
| Construction duration |
36 months |
| Occupancy |
September 2009 |
|